What did we do?

A project consisting of 207 properties

Client

Bluestone Design & Construction

Main Contractor

AMEY

Supply Duration

10 months

Scope of works

Tiled roof strip and retile to 207 residential properties, including fascia and soffits, canopies, loft insulation and chimney demolition, 

 

Phase 1 – 77 roofs coming to conclusion, on programme/time

 

Phase 2 – 130 roofs

With AMEY/MOD cleared operatives few and far between, we worked with Bluestone to get our lads through the process of completing and submitting paperwork to obtain AMEY clearance to enable them to work on MOD sites.

Operatives Supplied:

Between 6-10 Fixers

Related Services

Book an appointment